Upper Rose Bar Enhancement Project

Partners: South Yuba River Citizens League, cbec eco engineering, Cramer Fish Sciences, Hansen Brothers Enterprises

Funders: California Department of Fish and Wildlife, Wildlife Conservation Board, and Yuba Water Agency

Background: The Rose Bar project site is located 2 river miles below Englebright dam on land recently acquired by the Yuba Water Agency. The purpose of this project is to create and enhance two spawning riffles for Chinook salmon and steelhead. Englebright Dam prevents gravels from moving downstream from upper portions of the watershed. In the Goldfields, the piles of hydraulic mining debris provide the gravel sizes necessary for spawning. However, because Rose Bar is so close to Englebright Dam which traps downstream movement of gravel, as the Yuba River erodes spawning gravel, there is no source of gravel to replace it. We designed these riffles to remain stable up to approximately 70,000 cfs and take advantage of gravel injected higher up by the Army Corps of Engineers. The main objective of this project is to add spawning sized gravels to the riverbed from locally sourced material. We will be sourcing the necessary gravel from hydraulic mine tailings in the uplands above the project and at the same time stabilizing the hillslope which will decrease the amount of mercury delivered to the Yuba River during rain events. The total area of the project is about 43 acres with about 5 acres of new spawning habitat.

The primary objectives of the Proposed Project are:

1) Increase the amount of high-quality spawning habitat by modifying hydraulic (i.e., depth and velocity) and substrate conditions to within the ranges preferred by Chinook salmon and steelhead during typical spawning periods.

2) Create a design that mimics natural morphological features (e.g., riffle, pool) that would not erode significantly through typical non-flood control related operations.

3) Reduce bank erosion in the gully that may be contributing mercury contaminated soil to the Yuba River. 

SYRCL and CFS team conducting redd surveys at Rose Bar control site Winter 2021
Photo of the site from 1921. You can see the mining in action and the pattern the dredger leaves behind.
Map of Rose Bar Project Site
Pre and Post Project photos
Redds observed in Project Footprint in September, November, and December of 2024

Project Landmarks

More Salmon, More Redds

Up Next

On October 2, 2024, Travis Beckt, Ecohydrologist Technician II for cbec eco engineering, took this drone footage of even more spawning salmon using the project area to build redds. Monthly post-project redd surveys began promptly… Read More

Chinook spawning in the project!

September 17, 2024

Danielle Conway, SYRCL’s Fisheries Restoration Program Manager, began post-project monitoring at our Rose Bar project. Two weeks after completing this restoration project we see the first of what we hope will be many… Read More

completion of the in-water construction phase

August 30, 2024

On August 30th, we completed the in-water construction phase of the Rose Bar project. This project enhanced two spawning riffles in the lower Yuba River with appropriately sized spawning gravel. These… Read More

Phase 2 of Habitat Construction Begins

July 15, 2024

On Monday July 15th, the Rose Bar spawning habitat project began in water work, placing spawning gravel in the Yuba River at Rose Bar. Two spawning benches will be built made up of sorted gravel and cobble from… Read More

Tree Planting Complete

November 10, 2023

On Friday, November 10, 2023, nearly 25 folks showed up to help us plant around 500 oaks and foothill pines at our Upper Rose Bar Restoration… Read More

Phase 1 Contruction Completed

November 4, 2023

Accomplishments: access road was finished, all building materials to complete phase two are stockpiled, site was… Read More

Material Sorting Continues

August 23, 2023

Hansen Brother’s aggregate processing plant is sorting approximately 2,100 tons of material per day. As of 8/23, about 20,000 tons of spawning gravel has been stockpiled for riffle augmentation next… Read More

Phase 2 habitat construction Begins

Phase 1 implementation kickoff

July 24, 2023

Construction officially kicked off on July 24th and things have been moving non stop since. This year, we will only be constructing the access road, sorting the material generated from grading and… Read More

Funding from WCB Awarded

May 25, 2023

SYRCL is awarded funding from the Wildlife Conservation Board in May 2023 to support… Read More

Pre-Project Monitoring Completed

December 31, 2021

Two consecutive years of Read More

Planning Funding Secured

April 4, 2020

SYRCL is awarded planning… Read More

Feasibility and Alternative Report Prepared

January 31, 2016

In 2016, SYRCL, with the support from Sierra Streams Institute, prepared a Feasibility and Alternative Report assessing the on-site gravel suitability and available spawning habitat… Read More